November/December
1998,
p.4
The East River Bridges: 17
Years of Reconstruction and Counting…
As the rehabilitation of four
major NYC bridges continues into its 17th year, cyclists and pedestrians
wishing to cross the Williamsburg, Manhattan, Queensboro and Brooklyn bridges
are inching closer to decent, and in some cases exceptional, facilities. The
future looks bright, albeit distant, in the case of the Manhattan (ready in
2008) and Williamsburg (2005) bridges.
Following is a brief update
on bike and pedestrian access to these East River crossings
Queensboro Bridge
NOW: The North Outer Roadway is open to bikes and pedestrians, except
between 2:30 PM and 7:30 PM when cyclists must take a shuttle bus across. The
approach on the Manhattan side forces southbound cyclists into a five-block
detour to get to Second Avenue.
Although the DOT was quick to respond to our requests that asphalt ramps be
installed for the NYC Century Bike Tour, the ramps were quickly removed,
frustrating users and flatting tubes once again.
COMPLETION: Nov. 1999
The South Outer Roadway will be completed in November 1999. A recent DOT
proposal would allow bicycles and pedestrians on the Outer Roadways, with the
North Outer Roadway closed to non-motorists during the AM rush and the south
side closed to them during the PM rush.
COMMENTS: Without a pathway designed exclusively for cyclists and
pedestrians, users will have to contend with a path riddled with car parts,
oil slicks, and potholes, and will be forced to negotiate approaches designed
for both bikes and cars. A shared lane will also deteriorate faster than an
exclusive bikeway.
Read the latest news about this
issue.
Williamsburg Bridge
NOW: Contrary to its earlier reports, the DOT has delayed opening the
interim pedestrian and bike walkway from July to "before the end of
1998" due to a purportedly low-hanging horizontal beam. Until then,
cyclists must continue to weave through the worn and weary metal-plated bike
and pedestrian path on the north side. To cross over to the temporary ramp on
the Manhattan side, they must now tackle four new flights of stairs.
COMPLETION: 2005
The final plans call for a 12-foot-wide bike path on the north side of the
bridge and an 8-foot-wide pedestrian path on the south side. The paths will
merge on the Manhattan side into an 18-foot-wide ramp that touches down in the
center of Delancey Street.
COMMENTS: Featuring the widest bike lane of the four bridges, the final
Williamsburg design is relatively deluxe. When completed, it will sport all
the basic amenities of a proper bikeway, including well-spaced, durable
lighting, and fully ramped, safe and convenient access on both the Manhattan
and Brooklyn sides. However, pedestrians will likely end up walking across the
north (cycling-only) path too and DOT should anticipate mixed use.
Read the latest news about this
issue.
Manhattan Bridge
NOW: Closed.
COMPLETION: 2008
The path on the south side of the bridge is complete, but workers are using it
as a construction staging area. Because of safety concerns created when moving
large girders and equipment, and the ongoing lead paint abatement, the DOT
won't open it until 2001. The final design, for 2008, includes separate bike
and pedestrian paths. Plans for the north side include a 10-foot-wide bike
path, with Manhattan-side access through the small park on Canal Street. The
pedestrian path will be located on the south side.
COMMENTS: Another decade is a long time to wait. This bridge is a
textbook case of how not to do things - it tilts 12 feet to the side each time
a train crosses.
Read the latest news about this
issue.
Brooklyn Bridge
NOW: Shared bike and pedestrian path, open 24 hours. Replacement of the
wood planks on the promenade drags on. Stored on the pedestrian lane, the
carpentry crew's portable construction bridge creates an obstruction for all
users, even in the absence of actual construction activity.
CONSTRUCTION UPDATE: In an effort to improve approaches to the bridge,
the DOT plans to build a ramp between the existing path on the main span to
Cadman Plaza on the Brooklyn side. DOT has not reached a final decision on the
plans for the Manhattan side approach, though it will be a substantial
improvement of existing conditions. We'll report on the design in the next
issue.
COMMENTS: $300 million of structural work on the bridge is almost
complete, but approaches continue to be a nightmare. Additionally, the
promenade is simply too narrow to handle the volume of cyclists and
pedestrians attracted to the landmark span.
Read the latest news about this issue.
High Bridge
In response to a flood of postcards sent to Parks Commissioner Henry
"Star Quest" Stern, the Parks Department has announced it will
pursue funding to reopen the unused High Bridge bike/ped network connection.
Once funding is secured next spring, Parks will inspect the High Bridge and
begin to stabilize its badly deteriorated structure. Parks will probably
install ramps for bikes and rehabilitate existing stairs over the next five
years. The estimated cost of bringing the bridge back to its former glory is
$6 million.
Read the latest news about this issue.
|