Bridges In Brief
Cyclists and pedestrians will
have a new Williamsburg Bridge path to use by late spring 1998, when the newly
constructed south walkway/bikeway will be completed. While the Manhattan
entrance involves a long, steep cyclist-defeating staircase, DOT officials say
the stairs are temporary. The final design is ramped.
One bridge downriver, the
southside Manhattan Bridge walkway is virtually complete, although DOT will
keep the path closed until April 2001. Officials say construction near the
walkway, lead paint abatement on the bridge, and the incomplete Brooklyn Plaza
Park entrance make the walkway unsafe. Design of the northside permanent
bikeway is getting underway.